Search Projects By: Project Map | Project Name | Project Phase | Project Type | Ward
Craig Ranch Maintenance Facility

Contact: Mark Rodgers, P.E., S.E.
(702) 633-2777
Phase: Design
Project No.: 10295
Bid No.: TBD
Ward No.: 4
Last Update: 02/02/10
Project Scope:
This project will be within the Craig Ranch Regional Park and will include a 2,500 sf office, 1,600 sf mechanics shop, on-site improvements, and a two-lane vehicular bridge across the Gowan Outfall Channel. The facility will allow for on-site maintenance of the Craig Ranch Regional Park.
Project Status, as of December 31, 2009: (updated on a quarterly basis)
Pre-final documents were submitted on December 21, 2009 and are under review. Staff anticipates that the project will be advertised for bids in early January 2010.
| Project Information |
Design |
Construction |
| Project Manager |
Mark Rodgers, P.E., S.E.
(702) 633-2777 |
TBD |
| Consultant |
Tate Snyder Kinsey Architects |
TBD |
| Award of Consultant Contract |
12/03/08 |
TBD |
| Consultant Notice-to-Proceed |
01/06/09 |
TBD |
| Bid Opening |
TBD |
n/a |
| Bid Award |
TBD |
n/a |
| Contractor |
n/a |
TBD |
| Contractor Notice-to-Proceed |
n/a |
TBD |
| Substantial Completion |
n/a |
TBD |
Notice of Completion
(acceptance by City Council) |
n/a |
TBD |
|