Las Vegas Wash Trail (Civic Center Dr to Cheyenne Ave)
Contact: TBD
Phase: Design
Project No.: 10321
Bid No.: TBD
Ward No.: 1, 2
Last Update: 02/02/10
Project Scope:
This project includes the design and construction of trail improvements adjacent to the Cheyenne Peaking Basin.
Project Status, as of December 31, 2009: (updated on a quarterly basis)
The Cheyenne Peaking Basin Park Master Plan was recently completed. Design of the trail element only is anticipated to start in early 2010.
| Project Information |
Design |
Construction |
| Project Manager |
TBD
|
TBD |
| Consultant |
TBD |
TBD |
| Award of Consultant Contract |
TBD |
TBD |
| Consultant Notice-to-Proceed |
TBD |
TBD |
| Bid Opening |
TBD |
n/a |
| Bid Award |
TBD |
n/a |
| Contractor |
n/a |
TBD |
| Contractor Notice-to-Proceed |
n/a |
TBD |
| Substantial Completion |
n/a |
TBD |
Notice of Completion