Las Vegas Wash Trails, I-15 Pedestrian Bridge

Contact: Manson Wong, P.E.
(702) 633-2793
Phase: Design
Project No.: 10275
Bid No.: TBD
Ward No.: 4
Last Update: 02/02/10
Project Scope:
This project consists of the design and construction of a pedestrian bridge over I-15 of the Las Vegas Wash Regional Trail System.
Project Status, as of December 31, 2009: (updated on a quarterly basis)
A bridge type design Charette was held September 17, 2009 and a bridge type was selected for recommendation. A project presentation is tentatively scheduled on January 25, 2010 for the Development Group. The consultant is currently working on the bridge structural report, geotechnical report, and drainage study.
| Project Information |
Design |
Construction |
| Project Manager |
Manson Wong, P.E.
(702) 633-2793 |
TBD |
| Consultant |
PBS&J |
TBD |
| Award of Consultant Contract |
12/05/08 |
TBD |
| Consultant Notice-to-Proceed |
04/13/09 |
TBD |
| Bid Opening |
TBD |
n/a |
| Bid Award |
TBD |
n/a |
| Contractor |
n/a |
TBD |
| Contractor Notice-to-Proceed |
n/a |
TBD |
| Substantial Completion |
n/a |
TBD |
Notice of Completion
(acceptance by City Council) |
n/a |
TBD |
|