In-Fill Roadway Program - FY 2008

Contact: Manson Wong, P.E.
(702) 633-2793
Phase: Design
Project No.: 10260
Bid No.: TBD
Ward No.: 1
Last Update: 02/02/10
Project Scope:
The Work generally involves construction of half-street improvements for roadway segments along Centennial Parkway, Pecos Avenue, Statz Street, Tropical Parkway, and Azure Avenue within the vicinity of City of North Las Vegas. The improvements primarily consist of removals of existing asphaltic concrete, roadway excavation and embankment, construction of curb and gutter, sidewalk, asphaltic concrete pavement, storm drain drop inlets, water and sewer mains and laterals, street lights, traffic signal pole relocation, fiber optic interconnects, signing and striping.
Project Status, as of December 31, 2009: (updated on a quarterly basis)
Being combined with In-Fill Roadway Program - FY 2007.
|
|
|
| Project Manager |
Manson Wong, P.E.
(702) 633-2793 |
TBD |
| Consultant |
n/a |
TBD |
| Award of Consultant Contract |
n/a |
TBD |
| Consultant Notice-to-Proceed |
n/a |
TBD |
| Bid Opening |
TBD |
n/a |
| Bid Award |
TBD |
n/a |
| Contractor |
n/a |
TBD |
| Contractor Notice-to-Proceed |
n/a |
TBD |
| Substantial Completion |
n/a |
TBD |
Notice of Completion
(acceptance by City Council) |
n/a |
TBD |
|