Losee Road Improvements, Phase I (Lake Mead Blvd to Alexander Rd)

Contact: Melissa Sharp
(702) 633-1245
Phase: Construction
Project No.: 10192
Bid No.: 1305
Ward No.: 2, 4
Last Update: 02/02/10
Project Scope:
This project includes pavement rehabilitation of 2.9 miles of Losee Road from Lake Mead Boulevard to Alexander Road. The methods of rehabilitation will be full-depth reconstruction, mill and overlay, or crack seal with slurry seal.
Project Status, as of December 31, 2009: (updated on a quarterly basis)
Sewer bypass work at the channel wash has begun. Sewer installation along Losee Road from the channel wash to Alexander Road is 50% complete.
| Project Information |
Design |
Construction |
| Project Manager |
Manson Wong, P.E.
(702) 633-2793 |
Melissa Sharp
(702) 633-1245
|
| Consultant |
PBS&J |
n/a |
| Award of Consultant Contract |
5/17/06 |
n/a |
| Consultant Notice-to-Proceed |
10/23/07 |
n/a |
| Bid Opening |
03/12/09 |
n/a |
| Bid Award |
06/03/09 |
n/a |
| Contractor |
n/a |
Southwest Iron Works |
| Contractor Notice-to-Proceed |
n/a |
07/06/09 |
| Substantial Completion |
n/a |
TBD |
Notice of Completion
(acceptance by City Council) |
n/a |
TBD |
|