Upper Las Vegas Wash Regional Trail, Phase I

Contact: Kevie Remynse, E.I.
(702) 633-1253
Phase: Construction
Project No.: 10186
Bid No.: 1320
Ward No.: 1, 4
Last Update: 02/02/10
Project Scope:
This project consists of the design of a new trail system for pedestrian circulation following the Upper Las Vegas Wash drainage alignment, between Deer Springs Way and Craig Road.
Project Status, as of December 31, 2009: (updated on a quarterly basis)
The notice-to-proceed was issued on November 30, 2009 to Western States Contractors, and construction has started. The contractor has removed the fencing and replaced fencing from Craig Road to Lone Mountain. Trenching for lighting conduit has commenced. This project shall be completed within 180 construction calendar days.
| Project Information |
Design |
Construction |
| Project Manager |
Clint Fujii, P.E.
(702) 633-2688 |
Kevie Remynse, E.I.
(702) 633-1253
|
| Consultant |
HDR Engineering |
n/a |
| Award of Consultant Contract |
08/15/07 |
n/a |
| Consultant Notice-to-Proceed |
08/22/07 |
n/a |
| Bid Opening |
07/16/09 |
n/a |
| Bid Award |
10/07/09 |
n/a |
| Contractor |
n/a |
Western States Contracting, Inc. |
| Contractor Notice-to-Proceed |
n/a |
11/30/09 |
| Substantial Completion |
n/a |
TBD |
Notice of Completion
(acceptance by City Council) |
n/a |
TBD |
|