North 5th Street Super-Arterial Improvements, Phase IB (Owens Ave to Lake Mead Blvd)

Contact: Lindell Loy, P.E., S.E.
(702) 633-2751
Phase: Construction
Project No.: 10179B
Bid No.: 1352
Ward No.: 1, 2
Last Update: 02/02/10
Project Scope:
The design acquisition of right-of-way and construction of improvements from Owens to Lake Mead, which may include six travel lanes and a dedicated transit facility; landscaped multi-use trails and raised median area, curb & gutter, street lights, traffic interconnect conduit and fiber optics, traffic signals and modifications, and appurtenances as needed.
Project Status, as of December 31, 2009: (updated on a quarterly basis)
City Council awarded the construction contract to Tand, Inc in the amount of $7,304,874 on November 4, 2009. The Pre-Construction meeting was held on December 30, 2009. The notice to proceed for construction was issued January 4, 2010.
| Project Information |
Design |
Construction |
| Project Manager |
Allan Fajardo, P.E.
(702) 633-2044 |
Lindell Loy, P.E., S.E.
(702) 633-2751
|
| Consultant |
Louis Berger Group |
TBD |
| Award of Consultant Contract |
02/01/06 |
TBD |
| Consultant Notice-to-Proceed |
04/04/06 |
TBD |
| Bid Opening |
09/15/09 |
n/a |
| Bid Award |
TBD |
n/a |
| Contractor |
n/a |
Tand, Inc. |
| Contractor Notice-to-Proceed |
n/a |
01/04/10 |
| Substantial Completion |
n/a |
TBD |
Notice of Completion
(acceptance by City Council) |
n/a |
TBD |
|