Gowan Outfall / Lone Mountain System

Contact: Joemel Llamado, P.E.
(702) 633-1230
Phase: Close-Out
Project No.: 10151
Bid No.: 1297
Ward No.: 2, 3
Last Update: 02/02/10
Project Scope:
This project includes the design of 1.5 miles of various reinforced concrete boxes within Lone Mountain Road, between Decatur Boulevard and Clayton Street. The construction of this facility will effectively mitigate flooding along Lone Mountain Road corridor by conveying the surface runoff and flows from the west into a storm drain system for discharging into the Gowan Outfall System.
Project Status, as of December 31, 2009: (updated on a quarterly basis)
City Council approved the filing of the Notice of Completion on October 7, 2009. All retention has been released.
| Project Information |
Design |
Construction |
| Project Manager |
Quang Phan, P.E.
(702) 633-2009 |
Joemel Llamado, P.E.
(702) 633-1230 |
| Consultant |
GC Wallce |
n/a |
| Award of Consultant Contract |
09/07/05 |
n/a |
| Consultant Notice-to-Proceed |
11/01/05 |
n/a |
| Bid Opening |
11/01/07 |
n/a |
| Bid Award |
12/05/07 |
n/a |
| Contractor |
n/a |
Meadow Valley Contractors |
| Contractor Notice-to-Proceed |
n/a |
01/22/08 |
| Substantial Completion |
n/a |
06/24/09 |
Notice of Completion
(acceptance by City Council) |
n/a |