Search Projects By: Project Map | Project Name | Project Phase | Project Type | Ward
Craig Road Grade Separation, Phase III

Contact: Bob Rixford, P.E.
(702) 633-1938
Phase: Close-Out
Project No.: 10093
Bid No.: N/A
Ward No.: 1, 4
Last Update: 08/04/09
Project Scope:
This project consists of the construction of an overpass / grade separation at the Union Pacific Railroad (UPRR) crossing. Improvements include an overpass with six travel lanes, traffic control devices, a realignment of Donovan Way, local drainage improvements, access ramp between an elevated Craig Road and Donovan Way, emergency breakdown lanes, and traffic signal modifications.
Project Status, as of June 30, 2009: (updated on a quarterly basis)
The project is now open and operating. Final punch list items have been completed. NDOT will close the project out during the next quarter.
| Project Information |
Design |
Construction |
| Project Manager |
Tom Brady, P.E.
(702) 633-1227 |
Bob Rixford, P.E.
(702) 633-1938 |
| Consultant |
n/a |
n/a |
| Award of Consultant Contract |
n/a |
n/a |
| Consultant Notice-to-Proceed |
n/a |
n/a |
| Bid Opening |
n/a |
n/a |
| Bid Award |
n/a |
n/a |
| Contractor |
n/a |
Frehner Construction |
| Contractor Notice-to-Proceed |
n/a |
n/a |
| Substantial Completion |
n/a |
TBD |
Notice of Completion
(acceptance by City Council) |
n/a |
TBD |
|